Cornerstone University’s science and technology building was completed in December of 2018. The three-story building features seven labs and teaching spaces for students in STEM programs. Weather and other delays caused the schedule to fall behind by nearly six weeks. Centerline applied a creative prefab solution and constructed the facade with 28 Sto Backup panels of variable heights ranging from 31 feet to 46 feet. The panels were hung in six days time, realizing a total savings of five weeks from the original schedule.

PROJECT DETAILS

  • 32,000 sq ft building
  • 28 Sto Backup panels installed in six days
  • Variable panel heights, ranging from 31 to 46 feet
  • Full window blocking and air/vapor barrier installed in factory